Advice
About Pumping Concrete.
Managing
the Pour.
The key to a successful concrete pump pour is to manage the pour from
ordering the pump and concrete, through organising the site, to supervising
to pumping operation.
Some guidelines are set out below to assist with planning a pump pour.



When ordering
a pump please give the following info:
·
Company name.
· Contact name and
telephone number.
· Full site address
including postcode if known.
· Date and time for
the pump, allow approximately 30 minutes for the pump operator to set
up the pump.
· Size of pump required.
· Volume and type
of concrete including any admixtures, additions, fibres etc.
· Brief description
of the pour e.g. footing, external slab, bridge deck etc.
· Any other special
requirements pipeline, second man etc.
To ensure
a safe and efficient pump pour, please supply the following:
·
A level area of hard standing, with no overhead obstructions,
on which to set up the pump.

· Clear access to
the pump for the truck mixers.
· Cement to grout
the pipeline - 1 x 25 kg bags per 10 metres of pipeline.
· Somewhere to deposit
excess concrete.
· A good pump mix
concrete. Your ready mixed concrete supplier will advise.
· A competent concreting
gang to lay the concrete.
· A suitable place
for the operator to wash the pump out at the end of the job. At least
1/3 cubic metre of concrete will be left in the pump after the pumping
operation.
· A good supply of
water will help the operator, though the pump does carry its own supply.
The sequence
of a typical pump pour:
·
The pump will arrive and the operator will liaise with
the contractor before setting up the pump, pipeline (if required) and
preparing the grout.
· The concrete mixer
truck will arrive and back onto the pump.
· The pump operator
will then grout the line and commence pumping. It is good site practise
to pump excess grout to waste, not into the pour.
· The concrete will
be placed into position using the boom where possible. Where ground-line
is used, the concreting gang will need to move the pipeline around as
the pour progresses.
· Cautionary
note: Concrete
is pumped at high pressure. All personnel should be made aware of the
risks and dangers associated with end hose usage.
· When the truck
mixer has discharged its load, the mixer chutes will be cleaned before
the mixer leaves. The chutes should not be washed into the hopper as this
could cause a blockage and affect the quality of the concrete.
· The next mixer
will then arrive, back on to the pump and discharge its load.
· At the end of the
pour, the pump operator will clean all the concrete from the pump and
pipeline. This operation will take approximately one hour, more if the
job involves a long pipeline.
· The pump operator
will then put the boom back into its travel position and load all the
ancillary equipment onto the pump.
· The job sheet will
then be prepared for the contractor to sign.
· The pump will then
leave site and travel back to the depot.
|
Advantages
of Using Concrete Pumps.
·
Pumping placement is faster than placement by other methods.
· Pumped concrete
can be placed in areas that are difficult or impossible to reach by other
placement methods.
· Pumping often results
in a savings in manpower and equipment cost and cycle time.
· Pumping can take
place under any weather conditions, including snow and rain, since the
concrete is protected from the elements during transport to the placement
area.
· Pumping can be
used when the space available for construction equipment is limited.
· Pumping concrete
frees cranes and hoists for other construction operations, such as delivering
materials.
· Pumped concrete
can be easier to handle because the flow of concrete is directed to the
exact spot of placement (whereas cranes and conveyors deposit large piles
of concrete that must be moved manually).
· Few obstacles can
block a concrete pumping pipeline. Pipelines can corner sharply, pass
through narrow spaces, travel over or under walls, etc.
· A continuous supply
of pumped concrete can help set a steady work pace for the placement crew,
thereby increasing productivity.
· A contractor can
vary the placement speed or add lines to fit the pace of the job.
· Flow of concrete
remains steady and controlled.
· Pumping concrete
allows a contractor to place floor slabs on upper floors before completing
the concrete work on lower floors. This provides protection from weather
when working on lower floors.
· For large pours,
multiple pumps can be set up, allowing several trucks to discharge at
the same time.
·
Effective pumping distances range up 300 metres horizontally,
and 100 metres vertically.
Concrete
Mix Design for Concrete Pumps.
·
The concrete mix design must be correctly proportioned
so that the concrete will flow easily and uniformly through the pipe.
The pipeline diameter should be 3-1/2 to 4 times greater than the maximum
aggregate size for pumped concrete. This helps ensure that the pipeline
will not become clogged.
· Another factor
in mix design is the slump of the pumped concrete. A higher slump will
cause concrete to flow more readily, making the concrete easier to pump.
However, an
excessively high slump can cause the concrete to separate, resulting in
plugs in the pump or line.
·
What makes concrete Pumpable? Pumpable concrete can be
pushed under pressure through a pipeline as a cylinder, separate from
the pipeline wall by a lubricating layer of water, cement, and sand (mortar).
A concrete mix must be such that the concrete can pass through reducers
in the pipeline system, and can go around bends in the line. In order
to obtain this type of pumpability, the mix must be dense, cohesive, and
have sufficient mortar. (Mortar required depends on the line size, efficiency
of concrete pump, and pressure available for pumping concrete).
Concrete
Pump Location.
·
The most important consideration relating to pump location
is pump accessibility.
· Ideally, space
for two concrete trucks - one unloading and one ready to unload - should
be provided at the pump hopper.
· Usually, pumps
should be located as closely as possible to the area to be concreted last.


Commercial & Domestic - Servicing Western Victoria & SE South
Australia - 7 days a week - 24 hours a day - 0427 236980
|